Sandy has a deck-specific submittal list, and two items on it stop jobs that were otherwise ready to dig.
Do you need a permit to build a deck in Sandy?
Yes, and Sandy asks for more paperwork than most. Sandy publishes a dedicated Residential Deck / Covered Patio permit type with its own required-document list, and it states plainly that all listed documents must be submitted before the permit can be processed. Applications go through the Sandy CityWorks portal.
Source: Sandy City Community Development — Residential Deck/Covered Patio submittal requirements. Read from the city’s own document and verified .
The numbers your drawings have to use
These come straight from the city’s published design criteria. They are what a plan reviewer checks a deck against.
| Criterion | Value |
|---|---|
| Architectural and structural plans | Elevation plus all structural components and connections |
| Grading / site plan | Scaled and dimensioned, with distances to every property line |
| Structural calculations | Engineer-stamped where required |
| Engineering trigger | A covered roof, or a deck over one level |
| SWPPP | One page, signed and initialled — required before excavation |
| Sensitive Area Overlay | Applies on 30% slopes; engineer-stamped grading plan may be required |
| Owner Builder Form | If you act as your own contractor |
Two of these catch people. The SWPPP is not needed to begin plan review but is needed before you break ground — so a permit can be in review while the thing that lets you dig is still missing. And a covered roof or a second level triggers engineering, which turns a two-week job into a design job.
The Sensitive Area Overlay — Sandy’s bench problem
Sandy runs east into the foothills, and property on 30 percent slopes falls inside the Sensitive Area Overlay. Inside the SAO, an engineer-stamped grading plan may be required, and whether it is required is determined by the City Engineer — not by the building counter and not by you.
For a deck this is the difference between a straightforward submittal and a surveyed, engineered one. If your lot is on the east side of the city and the ground falls away behind the house, find out where you stand before you design anything.
Two different people, two different questions
Sandy publishes separate contacts for the two things most likely to hold a deck up: the Building Department for whether your plans need engineering, and the City Engineer for whether the Sensitive Area Overlay applies to your lot. Asking the wrong one costs a week.
Who to talk to at the city
Sandy City Community Development, 10000 S Centennial Pkwy, Sandy, UT 84070. Phone 801-568-7100. Permits, status and inspections through the Sandy CityWorks portal · building permits and submittal lists.
Check the Sensitive Area Overlay before you price the job. An engineer-stamped grading plan is a real cost and a real delay, and on Sandy’s east bench it is common enough that quoting without checking is guessing.
We handle this part