Midway pays for your inspection if it cannot get to you in three days. Very few cities tell you that.
Do you need a permit to build a deck in Midway?
Yes, and you pay a plan review deposit before anyone looks at it. Midway requires a plan review deposit receipt uploaded before submittal — $100 for additions, alterations, remodels and some repairs, which is the band a deck falls in. Everything is electronic and PDF, and incomplete applications are returned for correction before they are accepted.
Source: Midway City Building Permits & Inspections. Read from the city’s own document and verified .
The numbers your drawings have to use
These come straight from the city’s published design criteria. They are what a plan reviewer checks a deck against.
| Criterion | Value |
|---|---|
| Plan review deposit — additions, alterations, remodels | $100, receipt uploaded before submittal |
| Plan review deposit — new homes | $1,050.25 |
| Submittal format | PDF only, electronic; use Chrome on Apple devices |
| Incomplete application | Returned for correction, not accepted |
| Inspection request deadline | 3:00 pm the day before |
| If the city cannot inspect within 3 business days | Third-party inspector, paid for by Midway City |
| Building official | Tex Couch, Building Official / Fire Marshal |
The deposit catches people out because it runs backwards from most cities. Midway wants the receipt uploaded before the application is submitted — not billed at issuance, not paid at the counter. Without it the submittal is not accepted, and the clock never starts.
Midway will pay for a third-party inspection if it runs late
This is the most useful thing on Midway’s building page and almost nobody knows it. Under a new Utah state law, if Midway City is unable to perform an inspection within 3 business days of a request — made before the 3:00 pm daily deadline — the contractor may call one of the city’s pre-approved inspection agencies, and Midway City pays for that inspection.
The catch is in the timing, and it is the opposite of what you would guess: if the contractor calls the third-party agency before the 3-day deadline has passed, the contractor pays. The right only exists once the city has actually run out of time.
Midway lists Shums Coda among its approved agencies. On a deck this rarely matters. In a busy summer, on a job where framing is open and weather is coming, it can be worth several days.
Applying
- Create an account and submit electronically — there is no paper route.
- All documents PDF. Midway specifically asks Apple users to use Google Chrome, which suggests their uploader has had trouble with Safari.
- Complete every form in full; incomplete applications come back before they are accepted.
- Inspections requested before 3:00 pm are aimed at the next business day.
Who to talk to at the city
Midway City Building Department — Building Official and Fire Marshal Tex Couch, 435-654-3223 ext. 107 · tcouch@midwaycityut.gov. Open Monday to Thursday, 7:30am–5:30pm · permits and inspections.
Midway and Heber are not interchangeable. They are ten minutes apart and both in Wasatch County, but Midway runs its own building department with its own deposit structure, its own portal and its own inspector. Heber’s 70 sq ft attached-deck threshold is a Heber rule, not a Wasatch Back rule.