Do you need a permit to build a deck in Heber City?
Usually yes. Heber City requires a permit for a deck attached to the house if the floor area is over 70 sq ft, if any one dimension is over 7 ft, if the stairs have 4 or more risers, or if it is roofed or has a pergola. A detached deck needs one once it passes 200 sq ft.
Source: Heber City Deck Permit Requirement Checklist (City of Heber, 2015 IRC). Read from the city’s own document and verified .
Decks attached to the house
Heber City treats a deck supported by the dwelling as outdoor habitable space. A permit is required when any one of these is true:
| Trigger | Code |
|---|---|
| Floor area exceeds 70 sq ft | R304 |
| At least one horizontal deck dimension exceeds 7 ft | R304 |
| Stairs to grade have 4 or more risers | R311 |
| A guard is required along the deck edge | R312 |
| The deck is roofed or has a pergola above it | R301 |
A platform that falls outside all of those is treated as a landing, and still has to be supported well enough not to fail.
Free-standing decks
A deck not supported by the dwelling is a detached accessory structure. A permit is required when any of these is true:
| Trigger | Code |
|---|---|
| Area exceeds 200 sq ft | R105 |
| Stairs to grade have 4 or more risers | R311 |
| Beams or joists are not preservative-treated lumber | R318 |
| Roofed, or carrying a pergola — engineering required | R301 |
| Over 600 sq ft — must be engineered | R403 |
Two details worth knowing, because they save money. A deck between 200 and 600 sq ft may sit on footings that do not extend to frost level. And a deck that is self-supporting, under 200 sq ft, and low enough to the ground that its beams and joists must be preservative-treated is not required to be permitted at all.
What Heber wants to see on the drawings
These come from the same checklist, and they are the things that get plans rejected:
- Ledger: if attached, a full-depth ledger lag bolted at 24″ on centre with ½″ diameter lag bolts or equal screws.
- Lateral restraint device at each end of the deck — and tension ties at each end wherever the deck needs engineering.
- Guards at 36″ minimum height once the walking surface is more than 30″ above adjacent grade, with spindle gaps no more than 4″.
- Stairs: rise 8″ max, run 9″ min, handrail 34″–38″ above the nose of the treads, handrail no more than 2″ diameter and returned to the post.
- Landing of at least 36″ × 36″.
- Joist size and spacing, hanger type, beam sizes and spans, overall dimensions, and the use of the room the deck is accessed from.
How the application actually works
- Everything is submitted online through heber.mycityinspector.com — plans and supporting documents as PDFs. There is no counter submission.
- Engineers and architects must seal, sign and date their work; digital signatures are accepted.
- Plans are reviewed first come, first served regardless of complexity. The city states initial review can take two weeks depending on workload.
- Corrections come back electronically through the same portal.
- You pay at the end of the review, before the permit is issued — not up front.
Who to talk to at the city
Heber City Building Safety Division, 75 N Main Street, Heber City, UT 84032. Chief Building Official Curt Davis — 435-503-4903. Building Permit Tech Kelly Rogers — 435-654-6330. General: hcbuilding@heberut.gov · submittal requirements.
One thing to check before you rely on this. Heber’s checklist is written against the 2015 IRC. Utah adopts the construction code statewide under Utah Code Title 15A, and the state baseline has since moved on, so a detail in the handout can lag the code the plan reviewer is actually working from. We confirm the current position with the building official on every job rather than assuming the handout is current — and so should anyone else quoting these numbers back at you.
We handle this part